First Article Inspection (FAI)

Last updated

Definition of First Article Inspection (FAI)

First article inspection (FAI) is the complete measurement and verification of the first parts made by a new or modified production process, checked against every requirement on the drawing and specification. In injection molding, the first articles usually come from the first production-intent shots of a new tool, with at least one part taken from each cavity. Every dimension, note and material requirement is numbered on a copy of the drawing, called a ballooned drawing, and the result for each is recorded on an FAI report. Dimensions are usually measured with a coordinate measuring machine (CMM), which probes the part to record its geometry in three dimensions. In aerospace, the standard AS9102 sets the format of the report, and other industries use the same method with their own forms.

Why First Article Inspection (FAI) Matters for Your Business

FAI catches design and tooling errors before they turn into production volume, so a dimension cut wrong in one cavity, a missed drawing revision or a substitute resin shows up in the report instead of in your warehouse. Correcting the tool at this stage costs much less than sorting or scrapping a shipment that has already reached you. If your tool is built in Taiwan or Southeast Asia, ask for the FAI report before the samples ship, so that any correction can be made while the tool is still at the toolmaker.

The value of a report depends on how much of the part it covers. Reports that list only a handful of critical dimensions, or measure parts from one cavity of a four-cavity tool, leave most of the part unchecked. Ask for the ballooned drawing with the report so you can see that every characteristic has a result, and compare any result outside tolerance with the deviations you have actually approved.

Plan to repeat FAI when the tool is modified or repaired, when the material or production site changes, and after a long break in production.

First article inspection proves that the first parts conform to the drawing, while a Production Part Approval Process (PPAP) submission proves that the production process can keep making conforming parts. An FAI report measures a small number of parts from the first shots. A PPAP adds a production run of usually at least 300 parts, capability studies, the control plan and a risk analysis of the process. In automotive work, the dimensional results inside a PPAP package do much the same job as an FAI report.
On a new mold, failed dimensions most often come from shrinkage that differs from the toolmaker's estimate, so some features come out larger or smaller than the drawing. Plastic shrinks as it cools, typically by about 0.4 to 0.7% for amorphous resins such as ABS and polycarbonate (PC), and by about 1 to 2.5% for semi-crystalline resins such as polypropylene (PP) and polyacetal (POM). Warpage, where the part bows because it cools unevenly, and short shots, where the cavity does not fill completely, are other common causes. Most dimensional problems are corrected by adjusting process settings or by removing steel from the tool, which is why toolmakers leave extra steel on critical features for the first trial.
The molder normally performs the first article inspection and sends you the report with the measured parts, and you then decide whether to approve them. For a critical part, you can check a few key dimensions on the samples yourself or ask an independent inspection company to repeat the measurement. Compare the two sets of results before you approve, because small differences in fixturing can change a reading.